This is the story of my house construction with a review of the builder, building materials and the difficulties faced. To read Part 1 of the story Click here
Land preparation and leveling
Land preparation and leveling work has to be done before work can be started for basement excavation. After running around and with the help of father's friend found out some persons for cutting down the coconut trees in the plot. They did the job in a day.
Got a taste of the things to come on the first day of ground preparation work itself. I went to the site where labourers were already present. They asked for some tools, went with them and bought the tools, came back to office which was 8 kms away.
Once I was about to start my office work I got a call from the labourers that they are in need of more tools without which they cannot start the work. Went back to site, bought the tools and stood there only to find out that they did not use it for the entire day. The ordeal had started.
Each day there was a story, sometimes good, sometimes bad, sometimes worse.
Decided to proceed with the carpentry work. If we start now, we could get the completed doors and window frames by the time basement is ready.
The carpenter came along with me to buy wood. I followed his advice and shortlisted a shop.
Months later when I had to buy some extra wood did I realize that I was taken in for a ride by the carpenter and the shop I chose based on his advice was not the best in terms of price or quality. The carpenter took me there since they gave him good commission.
Earth excavation was over in around 20 days, but for me, it seemed that it took ages.
Land preparation and leveling work has to be done before work can be started for basement excavation. After running around and with the help of father's friend found out some persons for cutting down the coconut trees in the plot. They did the job in a day.
Got a taste of the things to come on the first day of ground preparation work itself. I went to the site where labourers were already present. They asked for some tools, went with them and bought the tools, came back to office which was 8 kms away.
Once I was about to start my office work I got a call from the labourers that they are in need of more tools without which they cannot start the work. Went back to site, bought the tools and stood there only to find out that they did not use it for the entire day. The ordeal had started.
Each day there was a story, sometimes good, sometimes bad, sometimes worse.
Decided to proceed with the carpentry work. If we start now, we could get the completed doors and window frames by the time basement is ready.
The carpenter came along with me to buy wood. I followed his advice and shortlisted a shop.
Months later when I had to buy some extra wood did I realize that I was taken in for a ride by the carpenter and the shop I chose based on his advice was not the best in terms of price or quality. The carpenter took me there since they gave him good commission.
Earth excavation was over in around 20 days, but for me, it seemed that it took ages.